Maemo.org Sprints/January 10
Contents |
[edit] January 2010 Sprint planning
- Planning meeting: Tuesday, 5th January 14:30 UTC in #maemo-meeting.
- Follows December 09. Precedes February 10.
[edit] Tasks
Ongoing tasks carried here from the previous sprint + New tasks committed by their owners in the sprint meeting. They come from the tasks in the Backlog and the Proposals.
Completed | Good progress | Just standing | Some help needed! | Really stuck/delayed |
Task ID | Task | Sprint priority | Owner | Percentage complete | Notes |
---|---|---|---|---|---|
9.10-07 | Server migration | Must | Ferenc | Done | Server move completed. |
9.11-08 | No orphaned pages and revise Wiki navigation | Must | dneary | 80% | See Wiki gardeners page for precise details, and Special:Lonelypages for progress. |
9.12-1 | Working bugzilla 3.4, migration path notes | Must | Andre, Karsten | 80% | |
10.01-01 | Refine the karma system | Must | VDVsx | DONE | Discussion here and here. Changes sent to the maemo.org team. App karma still need to be refined. |
10.01-02 | Testing Squad | Must | VDVsx | Done | Discussion here and here. Team created, gathering members. |
10.01-03 | Document processes for maemo.org infrastructure - dneary | Must | dneary | 50% | Niels has been busy with server moves, and hasn't had a chance to talk to me this month. Ferenc will be documenting the server set-up during the move. |
10.01-04 | Co-ordinate Maemo presence in FOSDEM - dneary | Must | dneary | DONE | There is Maemo content in 4 or 5 different tracks, and a Maemo night out on Saturday |
9.09-01 | Push packaging policy updates | Should | X-Fade, danielwilms | 60% | Unfortunately more changes needed than expected, not completed yet |
9.09-10 | Implement SSO sync-API endpoint for garage | Should | danielwilms | 80% | implemented new server instance for midgard account-sync, cas change from ldap to MySQL, certificates in place for endpoint-sync |
9.11-17 | Implement new UI for the application-downloader | Should | danielwilms, wazd | Done | changes in REST-API done, now completing UI changes |
9.12-5 | BMO: maemo.org custom features backport, Nokia patches | Should | Andre, Karsten | 25% | |
9.12-7 | BMO: CSS, maemo.org style | Should | Andre, Karsten | 0% | |
10.01-09 | Maemo User Experience Framework presentation | Should | Randall Arnold | 30% | proposed methodology for enabling bug reporting, app rating and similar user activities on devices |
10.01-05 | Setting up CAS & Midgard2 to use the same database | Could | danielwilms, indeyets | Done | At the moment separated for initial testing. |
10.01-06 | Midgard & Midgard2 data sync | Could | indeyets | 0% | Implemented already, needs to be enabled and tested |
10.01-07 | Wiki & Midgard2 data sync | Could | danielwilms | 0% | Component of gforge can partly be reused |
10.01-08 | Enable CAS for Midgard | Could | indeyets | 0% |
[edit] Actions
None yet
[edit] Activity log
Latest activity report goes on top. Activity will be reported here, Qaiku #maemork channel (Atom feed) or talk.maemo.org.
See latest sprint for activity